Sixth Annual Conference of the
International Group for Lean
Construction (IGLC-6 ) Guarujá, Brazil, 13-15 August 1998 Coordination: Glenn Ballard, Antonio Sergio Itri Conte, Gregory Howell, and Iris D. Tommelein |
|
Sessions |
|||||
|
1 - Theory |
2 - Design |
3 - Process |
4 - Planning |
5 - 6 Implementation |
7 - Case Studies |
|
Ballard - What Kind of Production |
Koskela - On the Agenda |
Alberto - Evaluating Building Systems |
Mendes - Preplanning Methodology |
Hirota - Construction Management Training |
Atkin - Unravelling the Value Chain in Construction |
|
Isatto - Design and Production Interface |
Alarcon - Improving Design |
Andery - Looking for what could be Wrong |
Choo - Workplan |
Barlow - Mass Customization |
Scola - Last Planner |
|
Formoso - The Principle of Transparency |
Mehlado - Designing for LC |
McManus - Practical Knowledge |
Finch - Embedded Internet |
Huovila - Sustainable Development |
Itri-Conte - Last Planner Lookahead |
|
Tommelein - Parade of Trades |
Patricia - Developing a Protocol |
  |
Formoso - Developing a Model for Small Sized Firms |
Kuprenas - Public Sector Case |
  |
|
Key Points |
|||||
|
Don't identify lean with product standardization |
Task, Flow and Value Management |
Alberto - Analyse building systems through a process analysis - LC/others. |
Integration: How to involve information and people through the planning process |
How to drive changes in Construction Industry |
One model from beginning to end |
|
Important to understand the application of LC Principles and approaches to construction better (including their interrelationships) |
Benefits of Design Process Modeling |
Failure Analysis Leading to Reliability Improvement |
Theory Proof and Technology is here. Let us use it. |
Beyond Lean - Is it Agile Production |
Beyond PPC - Resource Allocation & Optimization |
|
Improvements - Market to Product, Product to Process, Process - Operation |
Design for Production Implementation |
Independent Information Management |
Implications of Remote Control and Management |
LC Contributes to Sustainable Development |
Implementing PPC |
|   |   |   |
Critical Factors for Successful Implemention of Production Planning and Control |
  |
Commercial requirements to project participants cannot be underestimated |
|
Discussion Points |
|||||
|
Terminology "Agile" is this another form? |
Role of design done by specialty constructors |
Need to model projects not commercial interests |
Relationship of PPC and performance |
Barlow - What does agile bring that is more than lean? |
Graphical presentation of flows |
|
Standard vs. Agile |
Is lack of assignment definition a major cause for planning failure? Role of lookahead planning |
How to extend Alberto's new technology to other areas - could use methods to judge innovations |
How do we get site engineers to pay attention and use tools |
VALUE is in Lean!!! |
How will Los Angeles implement lean in contractors and consultants |
|
Distributed decisions and transparency |
Mixing task/flow/value - Where to focus? Level of concentration - methodology |
More about automatic information |
How does WorkPlan interface with CPM? |
Is it possible to concentrate on flow on site. |
What else after the Lookahead & PPC |
|
Knowledge retention |
Starting when design not ready |
Is failure analysis different |
Interplay between theory & technology |
Action Learning - more about |
Can CPM do this is a dynamic way/ |
|   |
Extent of design practice - do we accept existing phases |
How would you see different information managers design/construct/integrate or all 3? |
  |
Relevance of Conversion/Flow/Value Generation to eductation itself. |
Do you really need to deal with money? |
|   |
Organizational structure - Is this the place to start |
  |   |   |
Who participates on site meetings |
|
PLUS |
MINUS/CHANGE |
|
Enjoyed the discussion |
Have the papers in advance |
|
Technical visit was instructive |
More time on theory |
|
Liked the whole meeting |
Compare PPC data |
|
Supported the 15 minute limit but need papers in advance |
Discussion groups on specific topics and then report out, |
|
Use last part of workshop for seminars |
|
|
Maybe add more on local construction culture |
|
|
Limit presentations to specific topics - can read the rest |
|
|
Panel on practice |
|
|
Orientation seminar for newcomers to lean |
|
|
More focus on customer value |
| Iris D. Tommelein | IGLC | Lean Construction Institute |